Kingdom Hall Site Info and Building Pictures

Site Pictures   Zip file of all pictures of Sept.12/13 weekend (2.3 meg.)


Article on quick build in Fort McMurray Today paper



Oct 9-11 This weekend we will complete the Kingdom Hall to the point to having a useable place of worship. This will include the interior finishing, heating and air conditioning, the floor covings, the seats  etc.
 
Construction Tent Setup  Duct section ready Painting begins Seats in place
Sheet Metal Workers Outside work continues Ceiling progresses Sound system tested
Floor tiles in place  Wall tiles set in place  Heating control panel 
Drywall  starts to go up Heating control panel goes in Vacuum built-in
Taping starts  Duct sections installed A/C units
Electrical work continues Taping nears competion Windows installed
Brick work finished at front Drop ceiling starts Seats arrive
Furniture assembly starts Finish wood work starts Frames brought in
Sign letering in progress Narinder hard at work Seat frames installed
Long-legged taper Supper being prepared Sound system installed Pan view of main auditorium


Oct 3-5 This weekend we worked on the landscaping, installed the main entrance door and painted the chair frames
      Photos courtesy of W.Peterson


Sept 21-27 This week we had a contractor finish the fascia and eaves troughs. On the weekend we completed the final grade of the lot and laid the sod, planted trees and built a rock garden.

    



Sept 18-20 1998 This weekend we completed the stucco on the outside, the insulation was installed in all the walls and the poly was stapled up on the walls and ceiling.

      
 



Sept.11-12-13 1998:  This weekend was the construction of the outside of the hall, including brick work shingles and fascia. Also the electrical, plumbing, sound, vac lines and other systems were roughed in.
 
  • Trusses arrive
  • Roof sections lifted into place
  • Layout begins
  • Entry roof section goes up
  • Framing Starts
  • Entry roof section in place
  • Saturday Morning break feast 6:00 am
  • Brick layers Start
  • More Lumber arrives
  • Plumbers doing rough in
  • Walls go up
  • Supper time line up
  • Roof sections built


  • July 27- Aug. 5  We completed the preparations for the Kingdom Hall build with the completion of the curbing, the Air Conditioner pad and the paving of the parking lot by Wilson Contracting. We now are waiting for the quick build weekend, which is going to happen this fall.
  •  Apron completed
  •  Air Conditioner Pad
  •  Tool Shed
  •  Paved parking lot
  •  More parking lot
  • Eager Publishers waiting for the new hall

  • July 23 - 26  This week we  laid in the rebar and attached the lines for the in floor heating system. On Saturday at 7:00 AM the concrete for the pad arrived. We used a concrete pump unit to place the concrete and by 11:00 AM the concrete was completely troweled and starting to set. The  4100 sq.ft. of pad took 11-1/2 truck loads of concrete. In the afternoon the form on the front was removed and the insulation for the footings was put in place



    July 12 - 19 This week we continued the forming of building pad. The plumbers came and roughed in the drains and water pipes. The electrical and telephone conduit was also trenched in. After we tamped the gravel fill for the pad for a firm bed for the concrete.

    July 7- 12 This week we had a contractor do the primary site filling and grading. Also the contractor laid the waterline across Gregoire Drive. We formed and placed the concrete curbs for the parking lot. We also started staking out the concrete pad for the building.