Project Start Date: Tue 12/29/98
Project Finish Date: Wed 5/12/99
1 | Start Project | |||||
2 | Initiating tasks | 1 | ||||
3 | Initial meeting with project sponsor | 1 | Kathy[50%],John[50%],Mary[50%] | |||
4 | Research similar projects | 3 | John | |||
5 | Draft project requirements | 4 | Kathy[50%],John | |||
6 | Review with sponsor and other stakeholders | 5 | Kathy[50%],John[50%],Mary[50%] | |||
7 | Develop project charter | 6 | Kathy | |||
8 | Charter signed | 7 | ||||
9 | Planning tasks | 8 | ||||
10 | Develop WBS | 8 | Kathy[25%],John[25%],Mary[25%],Chris[25%] | |||
11 | Estimate durations | 10 | Kathy[25%],John[25%],Mary[25%] | |||
12 | Assign resources | 10 | Kathy[10%] | |||
13 | Determine task relationships | 10 | Kathy[10%] | |||
14 | Enter cost information | 10 | Chris[50%] | |||
15 | Review Gantt and PERT chart information | 13 | Kathy[25%] | |||
16 | Review plan with stakeholders | 11,12,13,15 | Kathy[25%],John[25%],Mary[25%],Chris[25%] | |||
17 | Executing tasks | 16 | ||||
18 | Analysis tasks | 16 | John[75%] | |||
19 | Design tasks | 18FS-10 % | Mary[75%] | |||
20 | Implementation tasks | 19FS-3 days | Mary[75%],Chris[75%] | |||
21 | Controlling tasks | 8 | ||||
22 | Status reports | 8 | Kathy[10%] | |||
23 | Status reports 1 | |||||
24 | Status reports 2 | |||||
25 | Status reports 3 | |||||
26 | Status reports 4 | |||||
27 | Status reports 5 | |||||
28 | Status reports 6 | |||||
29 | Status reports 7 | |||||
30 | Status reports 8 | |||||
31 | Status reports 9 | |||||
32 | Status reports 10 | |||||
33 | Status reports 11 | |||||
34 | Status reports 12 | |||||
35 | Status reports 13 | |||||
36 | Status reports 14 | |||||
37 | Status reports 15 | |||||
38 | Status reports 16 | |||||
39 | Status reports 17 | |||||
40 | Enter actuals | 8 | Chris[5%] | |||
41 | Review reports | 8 | Kathy[5%] | |||
42 | Adjust plan, if needed | 8 | Kathy[25%] | |||
43 | Closing tasks | 20 | ||||
44 | Prepare final project report | 20 | Kathy,John,Mary,Chris | |||
45 | Present final project to stakeholders | 44 | Kathy,John,Mary,Chris | |||
46 | Prepare lessons learned | 45 | Kathy[25%],John[25%],Mary[25%],Chris[25%] | |||
47 | End Project | 46 |