Project Start Date: Tue 12/29/98
Project Finish Date: Wed 5/12/99

Task_Data

IDTask_NameDurationStart_DateFinish_DatePredecessorsResource_Names
1Start Project0 daysTue 12/29/98Tue 12/29/98  
2Initiating tasks12 daysTue 12/29/98Wed 1/13/991 
3Initial meeting with project sponsor1 dayTue 12/29/98Tue 12/29/981Kathy[50%],John[50%],Mary[50%]
4Research similar projects5 daysWed 12/30/98Tue 1/5/993John
5Draft project requirements6 daysWed 1/6/99Wed 1/13/994Kathy[50%],John
6Review with sponsor and other stakeholders1 dayMon 1/11/99Mon 1/11/995Kathy[50%],John[50%],Mary[50%]
7Develop project charter1 dayTue 1/12/99Tue 1/12/996Kathy
8Charter signed0 daysTue 1/12/99Tue 1/12/997 
9Planning tasks11 daysWed 1/13/99Wed 1/27/998 
10Develop WBS5 daysWed 1/13/99Tue 1/19/998Kathy[25%],John[25%],Mary[25%],Chris[25%]
11Estimate durations5 daysWed 1/20/99Tue 1/26/9910Kathy[25%],John[25%],Mary[25%]
12Assign resources4 daysWed 1/20/99Mon 1/25/9910Kathy[10%]
13Determine task relationships2 daysWed 1/20/99Thu 1/21/9910Kathy[10%]
14Enter cost information3 daysWed 1/20/99Fri 1/22/9910Chris[50%]
15Review Gantt and PERT chart information1 dayFri 1/22/99Fri 1/22/9913Kathy[25%]
16Review plan with stakeholders1 dayWed 1/27/99Wed 1/27/9911,12,13,15Kathy[25%],John[25%],Mary[25%],Chris[25%]
17Executing tasks69 daysThu 1/28/99Tue 5/4/9916 
18Analysis tasks20 daysThu 1/28/99Wed 2/24/9916John[75%]
19Design tasks34 daysTue 2/23/99Fri 4/9/9918FS-10 %Mary[75%]
20Implementation tasks20 daysWed 4/7/99Tue 5/4/9919FS-3 daysMary[75%],Chris[75%]
21Controlling tasks80.13 daysWed 1/13/99Wed 5/5/998 
22Status reports80.13 daysWed 1/13/99Wed 5/5/998Kathy[10%]
23Status reports 11 hrWed 1/13/99Wed 1/13/99  
24Status reports 21 hrWed 1/20/99Wed 1/20/99  
25Status reports 31 hrWed 1/27/99Wed 1/27/99  
26Status reports 41 hrWed 2/3/99Wed 2/3/99  
27Status reports 51 hrWed 2/10/99Wed 2/10/99  
28Status reports 61 hrWed 2/17/99Wed 2/17/99  
29Status reports 71 hrWed 2/24/99Wed 2/24/99  
30Status reports 81 hrWed 3/3/99Wed 3/3/99  
31Status reports 91 hrWed 3/10/99Wed 3/10/99  
32Status reports 101 hrWed 3/17/99Wed 3/17/99  
33Status reports 111 hrWed 3/24/99Wed 3/24/99  
34Status reports 121 hrWed 3/31/99Wed 3/31/99  
35Status reports 131 hrWed 4/7/99Wed 4/7/99  
36Status reports 141 hrWed 4/14/99Wed 4/14/99  
37Status reports 151 hrWed 4/21/99Wed 4/21/99  
38Status reports 161 hrWed 4/28/99Wed 4/28/99  
39Status reports 171 hrWed 5/5/99Wed 5/5/99  
40Enter actuals60 daysWed 1/13/99Tue 4/6/998Chris[5%]
41Review reports60 daysWed 1/13/99Tue 4/6/998Kathy[5%]
42Adjust plan, if needed1 dayWed 1/13/99Wed 1/13/998Kathy[25%]
43Closing tasks6 daysWed 5/5/99Wed 5/12/9920 
44Prepare final project report3 daysWed 5/5/99Fri 5/7/9920Kathy,John,Mary,Chris
45Present final project to stakeholders1 dayMon 5/10/99Mon 5/10/9944Kathy,John,Mary,Chris
46Prepare lessons learned2 daysTue 5/11/99Wed 5/12/9945Kathy[25%],John[25%],Mary[25%],Chris[25%]
47End Project0 daysWed 5/12/99Wed 5/12/9946