By
BRIAN WILLCOX
of
ACTION MRPII
Capacity available is the capability of a system or resource to produce a quantity of output in a particular time period. (APICS Dictionary 9th Edition).
The question we are often faced with is how to establish how much capacity we have available in our plant.
There is two different ways of determining this.
Capacity can be calculated by taking into account the number of machines, the hours worked etc. This is termed rated capacity. The alternative is to measure capacity by averaging the performance in previous periods. This is termed demonstrated capacity. We will examine the two methods in turn.
l The number of machines or men in the work center.
l The number of shifts worked per day.
l The number of days per week the work center will work.
l How many hours overtime is scheduled as a percentage increase to a normal scheduled shift or work week.
l The utilization of the work center. This is usually taken from history.
l The efficiency of the work center, again taken from history.
These factors are multiplied together to calculate the available rated capacity
Rated capacity = 2 x 8 x 5 x 6 x 1.1 x 0.9 x 0.9
= 427.7 Std Hrs per week.
With the introduction of the theory of constraints, rated capacity is calculated in a different way.
Traditionally the hours that are available equals the clocked time scheduled, whereas with the TOC principle availability is the time the machine is actually available and fit to be used.
l Activation
This replaces the traditional utilization
and is the number of hours we need to use the machine for scheduled production,
versus the time it is available.
Other names for demonstrated capacity are the measured capacity, or the actual capacity. Demonstrated capacity is the real world. It is established by averaging the actual output, in standard hours, produced during previous periods.
Demonstrated capacity is defined as the proven capacity calculated from actual performance data, usually expressed as the average number of items produced multiplied by the standard hours per item.
Demonstrated capacity is the capacity that has been proven time and time again; it is not just the standard hours that can be produced, but also the standard hours that historically have been produced repeatedly.
l Total the standard hours for the ten weeks.
l Average the ten weeks; this indicates the
average output. This can then be used as the demonstrated capacity. See the
table below.
No. Produced
1 370
2 401
3 395
4 400
5 380
6 403
7 414
8 375
9 412
10 390
Total 3940
Average per week = 3940
= 394 Std Hours
A further point worth considering is the assumption that the demonstrated output will continue, but that is only true if the circumstances at the manufacturing work center remain the same. For example, if the product mix changes, or if we upset the labor force, then the volume of standard hours we do produce will change. We need to apply the knowledge of these factors to the capacity figure before using it.
| iSCM Articles | MRP II Articles | iSCM Library | iSCM Home|