The following is the construction time log for Song Weaver . Shown is actual construction time including drawing and transfering lines, cutting, gluing, assembling, painting, etc., etc. Not included is the time spent studying the plans and construction notes, shopping, cleanup, and, of course, cleaning the garage so we have the space to build her.

Date Activity Time This Date Time Accumlated
Feb. 20, 1999 Transfered frame side and bottom patterns to stock 5 hours 5 hours
Feb. 21, 1999 Transfered frame patterns and began cutting frame members 5 hours 10 hours
Feb. 22, 1999 Cut frame members 1/2 hour 10 1/2 hours
Feb. 23, 1999 Cut frame members 1 1/2 hours 12 hours
Feb. 27, 1999 Cut deck beams. Final shaping of frame members & deck beams 5 hours 17 hours
Feb. 28, 1999 Final shaping of frame members 6 hours 23 Hours
Mar. 1, 1999 Final shaping of frame members 2 hours 25 hours
Mar. 6, 1999 Final shaping of frame members 1hour 26 hours
Mar. 7, 1999 Cut floors and gussets. Layout frame #3 8 hours 34 Hours
Mar. 9, 1999 Assemble & glue frame #3 2 hours 36 hours
Mar. 10, 1999 Layout, assemble & glue frame #2 3 hours 39 hours
Mar. 11, 1999 Layout, assemble & glue frame #4 2 1/2 hours 41 1/2 hours
Mar. 12,1999 Notch frame members #1 1 hour 42 1/2 hours
Mar. 13, 1999 Layout frame #1 2 hours 44 1/2 hours
Mar. 14, 1999 Assemble & glue frames #1 & #5 3 1/2 hours 48 hours
Mar. 20, 1999 Transfer & cut transom, breast hook(s). Transfer stem. 8 hours 56 hours
Mar. 21, 1999 Cut out and laminate stem. Cut transom frames and assemble transom. 8 1/2 hours 64 1/2 hours
Mar. 22, 1999 Glue up transom 1 hour 65 1/2 hours
Mar. 28, 1999 Shape stem 1 1/2 hours 67 hours
Apr. 2, 1999 Frame gussets (reverse side) 2 hours 69 hours
Apr. 3, 1999 Correct miscut on stem; Fit breasthook to stem 5 1/2 hours 74 1/2 hours
Apr. 4, 1999 Laminate breasthook. Fit frame #5 to stem. Saturate one face of stem. 5 1/4hours 79 3/4 hours
Apr. 10, 1999 Epoxy saturation of sub assemblies 2 hours 81 3/4 hours
April 13, 1999 Epoxy saturation of sub assemblies. Glue stem/breasthook assembly 2 hours 83 3/4 hours
April 14, 1999 Epoxy saturation of sub assemblies 3/4 hour 84 1/2 hours
April 16, 1999 Epoxy saturation of sub assemblies 1/2 hour 85 hours
April 17, 1999 Epoxy saturation of sub assemblies 1/2/ hour 85 1/2 hours
April 18, 1999 Epoxy saturation of sub assemblies 2 hours 87 1/2 hours
April 19, 1999 Epoxy saturation of sub assemblies 2 hours 89 1/2 hours
May 2, 1999 Scarf base member for set up assembly 1 1/2 hours 91 hours
May 4, 1999 Bolt base member to shop floor 2 hours 93 hours
May 8, 1999 Work on setup 1 hour 94 hours
May 15, 1999 Work on setup 1 hour 95 hours
May 22 Work on setup 1/2 hour 95 1/2 hours
May 24, 1999 Work on setup 1/2/hour 96 hours
May 25, 1999 Work on setup 1/2 hours 96 1/2 hours
May 29, 1999 Work on setup 2 1/2 hours 99 hours
May 30, 1999 Work on setup; Carve insignia on deck beam 4 hours 103 hours
May 31, 1999 Work on setup; Hang stringer 3 1/2 hours 106 1/2 hours
June 5, 1999 Resquare setup 1/2 hour 107 hours
June 6, 1999 Hang stringers; Notch and fit frame #1 4 hours 111 hours
June 9, 1999 Port side stringer adjusted 3/16" 2 hours 113 hours
June 13, 1999 Stringer uprights and frame blocking cut 2 1/2 hours 115 1/2 hours
June 17, 1999 Work on setup 1/2 hour 116 hours
June 21, 1999 Work on setup 2 hours 118 hours
Work on setup 3 hours 121 hours
Work on setup 1 1/2 hours 122 1/2 hours
Work on setup 2 hours 124 1/2 hours