The Heightening of the Roseris Dam

By Eng. Mohammed AbdAllah AbduAllahi


(The Chief of Studies & Research Department of the Roseris Dam Heightening)
Reference: pp. 18-20, ElMouhandis, Vol. 5, No. 2, December 1996 (in Arabic)
Translated by Dr. Y. H. Ahmed

Introduction

The heightening of the Roseris Dam is considered the second and final stage of the construction of the dam. The foundations of the dam were built to support a concrete dam to construct a reservoir that provides for 490 m of water level (above the sea level). In the first stage in 1966, the concrete dam was only built to provide for a water-level of 480 m. The heightening of the concrete dam by 10 m will increase the reservoir capacity from 3 Milliard cubic metres to 7 Milliard cubic metres.

Objective of the Project

  1. Full utilisation of the Sudan share from the Nile Waters Agreement -1959.
  2. Strategic storage to face the outbreak of drought periods that occur in the sub-Saharan Africa.

Benefits of the Project

  1. Guarantee of the water demand for the irrigated schemes on the Blue Nile banks. This will stop the need to cut down the irrigated area in the drought years.
  2. Supply of water for rehabilitation of the pump-irrigated schemes on the Blue Nile that allows the expansion of these schemes.
  3. Supply of water for expanding projects like the Greater Kenanna and the second stage of Al-Rahad Scheme.
  4. Increase the capacity of hydropower generation by about 45% of the current capacity.

Components of the Project

Cost of the Project

The total cost of the project is estimated to be 360 Millions American Dollar, distributed as follows:

  1. Earth-dam (160 Millions).
  2. Concrete-dam (75 Millions).
  3. Equipment (60 Millions).
  4. Preliminary Works (30 Millions) &
  5. Consultants and project management (35 Millions).

Funds for the Project

The Ministry of Finance (Sudan Government) is the sole fund provider for this project. It is recognised that about 60% of the total cost can be provided in local currency, while 40% of the total cost is required as hard currency to import the electrical & mechanical equipment and steel, and pay the consultants. Due to the lack of foreign funds, foreign companies did not submit tenders for the construction of earth- & concrete-dams. The Ministry of Finance was able to get an equivalent of 22 Millions American Dollars loan in local currency from the Islamic Development Bank-Jeddah to fund the dam heightening. The expenditure from this loan has started in 1996/1997 on the earth-dam works.

Plans for Construction

The basic strategy of the construction is to maximise the utilisation of the local expertise in the project, established a special executive unit for this project.consequently:

  1. The earth-dam works was contracted to the Public Corporation for Excavation & Irrigation Works which
  2. The consultants were selected from national experts with exception to the highly specialised fields when foreign consultants have been employed.

Construction Programme

It was planned, provided that all the qualitative and quantitative funds are available, to finish the whole project in a six years period; 3 years for the construction of the concrete dam and 6 years for the construction of the earth-dam which will be carried out in parallel with the concrete dam construction. But, the reality of lacks of funds has made this impossible and the construction is constrained with the seasonal and annual variations of the fund situation. This, of course, makes it difficult to visualise any realistic time scale for finishing the project.


Back to the Index of Abstracts from ElMouhandis


Back to SESUKI Main Home Page


Visit The Editor's Homepage
This page hosted byGeoCities Get your own Free Home Page
1