October 98 - Plans
November 98 - Site work and well drilling at the farmhouse
November 98 - Well drilling at the new house
November 98 - Transit work
December 98 - Driveway
January 99 - Garage
April 99 - Revised Plans
May 99 - Excavating
June 99 - Staining
June 99 - Electrical service entrance
June 99 - Footing
July 99 - Pouring the walls
July 99 - Stripping the walls
July 99 - Electric
July 99 - Tarring, Insulating, and Backfilling the Foundation
July 99 - Setting the sill plates
July 99 - Building the wine cellar
August 99 - Building the first floor platform
August 99 - Framing
September 99 - Roofing, Sheathing, Windows - Closing in
October 99 - Siding
October 99 - Fall Foliage Views
October 99 - Wiring
November 99 - Septic system
November 99 - Basement Framing and Wood Stove
November 99 - Rough Landscaping
November 99 - Heating and Cooling System
May 00 - Framing and Wiring
May 00 - Plumbing
June 00 - Insulation
June 00 - Sheetrock
June 00 - Master Bathroom
June/July 00 - Stairs
July/August 00 - Fireplace Tiling
September 00 - Flooring
September/October 00 - Painting/Finish Electrical
October 00 - Finish Plumbing
November 00 - Gutters and drain lines
November 00 - Interior trim and fittings
November 00 - Kitchen Stove, Cabinets, and Countertops
May 01 - Finishing touches
June 01 - Finishing touches
July 01 - Finishing touches
August 01 - Finishing touches
August 01 - Hot tub
August 01 - Ponds
October 01 - "Final" photos