Subject: Ratchaburi power plant
      The Nation
      Thurs, Feb 19, 1998

      Ratchaburi power

      plant in for delay

      Egat officials confirmed yesterday
      that completion of the massive
      Ratchaburi power plant will be
      delayed, threatening the country with
      blackouts and raising new questions
      about the timetable for the Yadana
      gas pipeline.

      Siridhat Klanklamdee, Egat's
      assistant governor, said construction
      of the first gas-fired unit, which is due
      to burn natural gas delivered by the
      pipeline from Burma starting in July,
      is likely to be delayed by about one
      month because of
      slower-than-expected progress from
      contractors building the plant.

      However, a senior Egat official said
      the delay could last around three
      months because of the recent
      Cabinet resolution to comply with the
      International Monetary Fund's
      balanced budget policy for all state
      enterprises, which has forced Egat to
      postpone payments to suppliers and
      creditors for many projects, including
      the Ratchaburi plant.

      ''Amid the slowdown in electricity
      demand, Egat could not convince the
      government to complete the power
      plant on time,'' said the Egat source,
      who asked to remain anonymous.

      The issue of Egat's financial liquidity
      problems was raised several days
      ago by the Kalayanamitra Council's
      Pipob Udomittipong, a pipeline critic
      who testified before the national
      committee set up to review the
      pipeline project. Pipob said Egat
      would not be able to pay off its
      suppliers until the new fiscal year
      starts after Sept 30, and predicted
      the first 200-megawatt
      combined-cycle unit of the Ratchaburi
      plant will not be ready to receive gas
      until November.

      The delay has created new
      uncertainties for the Petroleum
      Authority of Thailand's pipeline
      project, which is currently being built
      through a pristine forest area in
      Kanchanaburi inhabited by several
      rare and endemic species. Critics
      have called for its route to be altered,
      which could become more feasible
      now that the power plant destined to
      use the gas won't be ready on time.

      The PTT's reaction to Egat's news
      yesterday was relatively mild. The
      PTT has in the past responded to
      calls by conservationists to delay the
      project by insisting it must be
      completed by July 1 or the company
      would have to pay fines as high as
      Bt100 million per day.

      Jira Chomhimvet, the PTT official
      who heads local operations for the
      project, revealed yesterday that while
      the PTT would indeed have to pay
      for the gas Burma is supposed to
      deliver even if the PTT can't receive
      it, the losses would be far less than
      suggested.

      ''We can eventually claim the gas we
      pay for once the power plant is
      finished and the country is ready to
      take it,'' Jira said. ''In the end, the only
      money we will lose will be the
      interest.''

      The senior Egat official also
      disclosed yesterday that executives
      from Egat and the PTT will soon go
      to Burma to ask Burmese authorities
      to relax the penalty charge should the
      PTT be unable to receive the
      Burmese gas on schedule.

      According to the source, the extra
      charge will be around Bt150-Bt170
      million a month, depending on the
      exchange rate at the time. He
      confirmed that the charge is not
      simply a penalty fee but rather an
      advance payment for the gas since
      some flexibility is allowed under the
      gas sales contract.

      He said Egat will help the PTT
      convince the Burmese about the
      reasons why the PTT cannot receive
      gas on time, even though Egat is not
      required to pay the PTT if the power
      plant is delayed.

      This contradicted comments made at
      the pipeline committee meeting by
      Egat's Siridat, who said Egat had
      signed a ''take-or-pay'' agreement
      with the PTT, and so must pay for the
      gas even if it cannot take it.

      Siridat said postponement of the
      commissioning of the Ratchaburi
      power plant will cause electricity
      brownouts and blackouts, each
      minute of which will cost the country
      Bt1.2 million.

      ''The economic cost will be doubled if
      the blackout occurs in big cities or
      industrial zones,'' he said.

      Without the Ratchaburi plant, the
      national electricity reserve capacity in
      1999 will stand at only 10.2 per cent,
      far lower than the 25 per cent
      minimum requirement. The current
      reserve capacity is 12 per cent,
      according to the assistant governor.

      ''We are well aware of the
      consequences [of the delay] and are
      speeding up construction of the
      project to try and finish it on time,'' he
      said.

      Meanwhile, the national committee
      reviewing the pipeline project wound
      up its information-gathering yesterday
      and will now deliberate on
      recommendations to offer to the
      prime minister next week.

      Testifying on the issue of safety
      concerns, the PTT's Vorachai
      Piyasuntaravongse told the
      committee that the petroleum firm has
      already paid insurance fees --
      totalling US$10 million for the
      pre-commissioning period and US$30
      million for the post-commissioning
      period -- to protect the lives of
      contractors, workers and people
      living along the pipeline route.

      The insurance also covers sabotage
      and damage to villagers' houses. If
      the businesses of people living near
      the pipeline are affected by the
      existence or construction of the
      pipeline, they can also seek
      compensation, he said.

      BY WATCHARAPONG
      THONGRUNG and PENNAPA
      HONGTHONG
 
  1