New House - July 99 - Tarring, Insulating, and Backfilling the Foundation

Tarring
Rick spreads the tar on the wall ...
insulating
... and sets a styrofoam panel into it.
finished
By the end of the day, Rick had tarred most of three sides
and Martha had set 60 of the two foot wide panels.
Finished west wall
The next morning brought a new bucket of tar and
the last few panels were placed on the west wall
where there is a double walkout door and a wine cellar.
Stone and drainage pipe
A truckload of no 2 stone arrived
and was placed around the footing.
Drainage pipe was placed on that and ...
trench for drainage
... a trench was dug so that the pipe
could reach the hedgerow and run downhill.
Building paper
More stone is placed on the drainage pipe and
the stone is then covered with building paper
to keep dirt from clogging the drainage system.
Water line from the well
Gould showed up to put in the water line from the well
and the electrical line to the submersible pump.
The foundation was inspected prior to backfilling to ensure that it was tarred and insulated and that the drainage tile was installed properly. The backfilling is necessary as the excavator must get close to the walls in order to reach over and lift the 36 ft 8WF31 steel beams into place across the cellar.

At about the same time, the electrical inspection was completed and faxed to NYSEG. On 15 July, the NYSEG foreman stopped in to check things over and said that the crew would be back the next day to install the two transformers and set the meter. Electricity, soon come. And it did.

Beams
Wayne Underwood backfilled the foundation
and set the beams on 18 July 99.

Jump to: the next phase | the new house page | Our Geocities home page | KC Travel Site

Last updated 19 July 99

1